by Christian Vitt

Step by step to the green combined heat and power plant with new turbine

The first important milestone for the customer, SWB Energie und Wasser – Stadtwerke-Bonn, was met on time by Heitkamp Industrial Solutions. The detailed coordinated schedule with all subcontractors and supplies was implemented at the construction site. The installation of the generator and the gas turbine was successfully carried out on 29.08.2022 and 30.08.2022.

The transport of the turbine and the generator by ship took place in the 34th calendar week, followed by loading and transport to the site. The SGT-750 generator has now found its place in the new nacelle, as has the new turbine.

Due to the tight space conditions and limited assembly opening, an electronically multi-directional module transporter was used for the transport. In the presence of the client and Siemens, the 120-tonne turbine was moved into the nacelle on the GT foundation in just a few hours and was successfully set down. All parties involved were very satisfied with the course of the quite complex installation.

Stadtwerke-Bonn – SWB Energie und Wasser

About us

Our company is looking back on a successful building tradition since 1892. Heitkamp stands for the optimal interaction of engineering know-how and constructional realisation.

Contact

HEITKAMP
Industrial Solutions GmbH
Bonsiepen 9 -11
45136 Essen, Germany

+49 (0) 201 / 8 36 90 - 0

+49 (0) 201 / 8 36 90 - 199

Socials

© 2026 HEITKAMP Industrial Solutions GmbH. All Rights reserved.
Settings saved
Privacy settings

Please make a selection to continue
We use cookies and similar technologies to improve your experience on our website. Some cookies are necessary for basic functionality, while others help us analyze usage and optimize our services. For detailed information, please see our privacy policy.

user_privacy_settings_expires

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves the privacy level settings from the cookie consent tool “Privacy Manager.”

user_privacy_settings_expires

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Stores the storage duration of the privacy level settings from the cookie consent tool “Privacy Manager.”

ce_popup_isClosed

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Stores that the popup (content element - popup) was closed by a click of the user.

onepage_animate

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Stores that the scroll script for the one-page navigation has been started.

onepage_position

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves the offset position for the one-page navigation.

onepage_active

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves that the current page is a “one-page” page.

view_isGrid

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves the selected list/grid view in the demo CarDealer / CustomCatalog List.

portfolio_MODULE_ID

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves the selected filter of the portfolio filter.

Eclipse.outdated-browser: "confirmed"

Domain name: heitkamp-solutions.com
Procedure: 30 days
Storage location: Localstorage
Description: Saves the status of the “Outdated Browser” notification bar.
You are using an outdated browser. The website may not be displayed correctly.